At 4 p.m., six shops remain on the seller’s list. They have worked all day, but two shopkeepers were absent and one journey took longer than expected. Before asking them to speed up, review your sales route planning: did the schedule realistically fit into the working day?
For a distributor in Algeria, a sales route is built around customers, distances and available time. This article, published by FULLLOYAL, offers a method for planning achievable visits and understanding those still outstanding.

Sales route planning: start with time, rather than a uniform quota
Two sellers can have the same number of customers and very different days. One visits several shops in a single neighbourhood. The other travels between distant towns and waits for particular decision-makers.
Before setting a visit target, separate travel time, time spent with customers and work outside visits. Depending on your organisation, the latter includes preparation, communication with the office and reporting.
Also allow time for unexpected events. A plan that already fills the whole day on paper will be difficult to maintain after the first delay.
Describe the work expected during each customer visit
A quick order may take a different amount of time from an initial product-range presentation. A visit may also include discussing customer debt or collecting a payment, if that responsibility belongs to the seller.
When preparing the schedule, distinguish a few simple situations:
- An existing customer placing a routine order.
- A new outlet requiring an introduction and qualification.
- A customer with a commercial issue to resolve.
- A short call to check a need or arrange an appointment.
These categories help estimate the work. They do not justify multiplying forms. Above all, ask the seller what explains lengthy visits and frequent waiting.
Group customers without ignoring their constraints
Build coherent territories and note the days or time slots when shops can receive your team. A nearby customer may still be impossible to visit if their decision-maker is never available at the planned time.
Also define the desired visit frequency for each shop. Some need regular calls; others can be visited less often, depending on their needs and your commercial agreements.
Avoid crossing the same territory repeatedly to complete a poorly organised list. When rescheduling a visit, check its impact on the other calls rather than simply adding it to the end of the day.
Fictional example: building a route with fourteen visits
Consider a business with five pre-sales representatives and three delivery drivers. The representatives take orders; the drivers follow a separate delivery schedule. This fictional example describes one representative’s day.
After the breaks planned by this organisation, the representative has 420 working minutes available. For the territory being tested, the manager uses the following assumptions:
| Time category | Assumption in this example |
|---|---|
| Preparation and work with the back office | 60 minutes |
| Travel within the territory | 120 minutes |
| Allowance for unexpected delays | 30 minutes |
| Time remaining for visits | 210 minutes |
Assuming an average of 15 minutes per visit, 210 ÷ 15 = 14 planned visits. The total is indeed 420 minutes: 60 + 120 + 30 + 210.
Planning 18 visits with the same assumptions would require 480 minutes, or 60 minutes more. The manager must therefore review the territory, visit allocation or expected work. Simply changing the number on the schedule cannot solve this difference.
These durations are planning assumptions, not an industry standard for distributors. Measure your own activity before adopting a target.
Distinguish completed visits, sales and postponed calls
A visit without an order does not automatically mean the seller did nothing. The shop may still have stock, be waiting for a decision or report a problem that needs attention.
In your records, separate customers visited, orders obtained and visits not completed. For the last category, retain a short explanation and a next action.
A closed shop, an absent decision-maker and insufficient time require different responses. You might change a time slot, arrange an appointment or reduce a route’s workload. Total sales alone cannot tell you which action to take.
Review the route plan with the seller
After a few representative days, compare assumptions with what happened. Does travel take longer? Do first visits last longer? Are the same shops regularly postponed?
Start by correcting recurring problems. Moving a customer to another day or grouping visits can be more useful than asking everyone on the team for the same additional effort.
In pre-sales, also coordinate commercial promises with the warehouse and delivery drivers. A visit that produces an order should not commit to a delivery date incompatible with the planned operation.
Using FULLLOYAL to follow field activity
FULLLOYAL combines an Android application and a web back office. The solution includes routes, visits and reports on field activity, as well as sales and stock.
The pre-sales representative profile takes orders without carrying goods. Delivery driver mode provides access to the delivery notes assigned to each driver. The application also supports offline work, with synchronisation when the connection returns.
To prepare a demonstration, bring a territory, a customer list and your team’s time assumptions. Ask how you would organise and follow this schedule. The word “route” alone does not establish the presence of automatic route calculation or GPS tracking.
FAQ
How many customers should a pre-sales representative visit each day?
There is no single number suited to every territory. Estimate available time, travel and visit duration. The fourteen calls in the example are not a universal target.
Should the pre-sales representative and driver use the same schedule?
Their responsibilities differ. The former takes orders; the latter delivers according to their assigned documents. Coordinate the schedules without assuming they must make the same stops on the same day.
How should a visit without an order be handled?
Record the visit and its outcome according to your procedure. Establish what should happen next: another visit, a commercial response or simply waiting. No order does not erase the visit.
Can routes be prepared in Excel before choosing an application?
Yes. A list by territory with frequency, preferred time slot and estimated duration can support an initial schedule. Check feasibility in the field before moving it into another tool.